Case Study 2 of 3 · Enterprise Web Application Launch Simulation
Flagship Case Study · Project Management · Self-Directed Simulation

Running Full Project Governance on an 8-Week Product Launch

Enterprise Web Application Delivery Simulation
Role
Project Manager (Self-Directed)
Duration
8 weeks · 40 working days
Team
9-person cross-functional team
Budget
$74,470 (incl. 10% contingency)

Planned and governed an end-to-end enterprise web application launch over eight weeks using industry-standard project management practices.

This self-directed simulation was created to demonstrate end-to-end project management capability using original governance documentation, project planning artefacts, and reporting dashboards developed independently.

What "done" had to mean

Schedule Success
Launch by Week 8 with a maximum approved schedule variance of two days.
Quality Standards
Zero critical defects, Lighthouse score ≥90, and WCAG 2.1 AA compliance.
Security & Governance
Zero critical penetration-test findings and formal stakeholder sign-off before release.
Operational Acceptance
UAT ≥4.0/5, delivery within the approved $74,470 budget, and 99.9% uptime target.

Six milestone gates, not just a schedule

Project Manager - Governance, Scheduling & Risk

Authored the charter, RACI matrix, 25-item risk register, and quality bar before any task began, then ran weekly gate reviews against them.

M1
Week 1
Kickoff Complete
Charter signed, requirements documented, Asana live with all 36 tasks.
M2
Wk 2–3
Wireframes Approved
Feedback within 48-hr SLA; no structural changes after sign-off.
M3
Wk 3–5
Design Handoff Complete
Hi-fi designs done, 5-user usability test, annotated dev handoff.
M4
Wk 3–6
Feature Complete
Staging deployed, code freeze, QA phase begins.
M5
Wk 6–7
UAT Sign-off
Zero critical defects, pen test passed, go/no-go granted.
M6
Week 8
Launch Day
Production live, monitoring verified, checklist complete.

Project Health - Week 5 of 8

Project Health - Real Simulation Data
Actual figures from the workbook
Overall Progress
42%
15.05 / 36 tasks
Weighted completion of all 36 Asana tasks against their estimated effort.
Milestones Hit
2 / 6
M1, M2 complete
Milestone gates formally signed off against their exit criteria.
Tasks On Hold
2
T12, T13 — blocked on T11
Tasks whose dependency has not yet cleared, tracked directly in the Gantt.
Total Budget Ceiling
$74,470
incl. $6,770 contingency
Sum of all task-level cost estimates plus a 10% contingency reserve.
Risks Identified
25
3 rated Critical
Total entries in the risk register, scored by likelihood × impact.
Team Size
9
cross-functional roles
Distinct roles assigned an owner in the RACI matrix.
RACI Activities
52
fully assigned
Activities in the RACI matrix with a Responsible and Accountable party named.
Stakeholders Tracked
12
tiered by influence
Stakeholders mapped by influence and interest in the communication plan.
Discovery
100%
Design
54%
Development
32%
QA & Testing
12%
Launch Prep
0%
Launch
0%

Weeks 1 - 8 at a glance

W1W2W3W4W5W6W7W8
Discovery
Design
  — Mobile UI (hold)
Development
QA & Testing
Launch Prep & Launch

Week 5 - a downstream chain paused, not the whole project

Desktop design (T11) ran behind at 65%. The two tasks depending on it were correctly held rather than started against an unfinished input.

Design Phase — Week 5 Snapshot
Live Gantt
T11
Hi-fi desktop UI design
Tunde Fashola
65% Active
T12
Hi-fi mobile/tablet design
Tunde Fashola
On Hold
T13
Usability testing (5 users)
Amaka Chukwu
On Hold
T18
Frontend design system
Yemi Coker
40% Active

6 of 25 identified risks, real data

risk_register.xlsx
IDRiskLevelOwner
R01Scope creep after approvalCriticalProduct Manager
R02Late stakeholder approvalsCriticalProject Manager
R22Inadequate testing coverageCriticalQA Engineer
R04Fragile codebase under time pressureHighTech Lead
R07Security weaknesses near launchHighTech Lead
R18Team fatigue reduces qualityHighProject Manager
Pulled directly from the 25-risk register — no redaction needed, this is self-authored simulation data

No gate passed unless every criterion below was met

Performance
≥90
Lighthouse score
Development
≥80%
Test coverage
Accessibility
0
WCAG 2.1 AA failures
Security
0
Open pen-test findings

Who had influence, and who needed to stay informed

Project Sponsor / CEO
Executive
High Inf.High Int.
CTO
Technology
High Inf.High Int.
CMO
Marketing
High Inf.High Int.
Beta User Panel
External / UAT
Low Inf.High Int.

What changed

📋
Governance Established
Built a complete project governance framework before execution, including the Project Charter, RACI matrix, RAID log, communication plan, quality gates, and stakeholder register, providing clear ownership and decision-making throughout the project.
📅
Structured Delivery
Implemented milestone-based governance with six formal stage gates, ensuring each project phase met predefined quality and approval criteria before progressing.
⚠
Proactive Risk Management
Created and actively maintained a comprehensive risk register, allowing project risks, assumptions, issues, and dependencies to be identified, monitored, and managed throughout delivery.
🤝
Stronger Stakeholder Alignment
Established structured communication and approval checkpoints that kept stakeholders informed, clarified expectations, and supported timely decision-making.
📊
Improved Project Visibility
Developed executive dashboards and progress reporting that provided a real-time view of project health, schedule performance, risks, milestones, and delivery status.
🚀
Delivery Readiness
Defined measurable success criteria covering schedule, budget, quality, security, accessibility, and user acceptance, ensuring the project was ready for release before launch approval.

What running this simulation actually taught me

What Worked
Governance gates prevented uncontrolled scope changes.
Weekly stakeholder reporting improved decision-making.
Early risk identification reduced downstream disruption.
What Could Be Improved
Design phase was under-resourced relative to its dependency load, one designer, two blocking tasks
QA planning (T26) started early but had no dedicated owner until Week 3
Earlier UX validation would have reduced redesign effort.

Download the Full Workbook

The complete project management workbook — schedule, risk register, RACI matrix, and budget — used to build this case study.

Download Project Workbook →